White River Greenway Initiative: Construction Updates- Summer/Fall 2026
CURRENT CONSTRUCTION UPDATE & PROGRESS PHOTOS
Eastern Park & Perkinsville Public Access Site Flooding & Construction Update
Historic flooding in August impacted both the Eastern Park construction site and the Perkinsville Public Access Site. As designed, floodwaters receded naturally at both locations, and none of the newly constructed infrastructure was damaged.
The Eastern Park site is located within a known floodplain, a condition understood and accounted for throughout the planning and design process. Parks and open spaces are commonly built in floodplain areas because they can accommodate periodic high water while keeping homes, businesses, and critical infrastructure out of harm’s way. The Eastern Park was designed to work with the natural landscape, including the reality that the White River will occasionally rise and portions of the site may temporarily flood.
The significant rainfall and saturated ground conditions have extended the construction timeline, primarily to provide the appropriate conditions for final planting, site restoration and remaining punch-list work. Construction at both sites is now anticipated to be substantially completed by early November with minor items by the end of November.
Madison County Parks and Recreation continues to work closely with the project team to ensure these improvements are completed thoughtfully and responsibly, with the long-term resilience and enjoyment of these riverfront spaces in mind.
Project Site Photos (09.03.26)
SEPTEMBER CONSTRUCTION UPDATE & SITE PROGRESS PHOTOS
White River Greenway Eastern Park
Current Site Work:
E&B’s path construction began 9/23
Staking for paths have been completed and grass is to be installed in the areas that have been staked but will not be stone
Intent is to allow for a mowed path that eventually can be converted stone
On/After 10/1 the maple tree at the end of the boat ramp will be cut down
Riprap work at boat ramp will happen after the tree has been cut to help allow for better grading and placement of material to protect the boat ramp
Mid-October, the HMA surface, pavement markings, and stone shoulder will be installed, trees will also be installed within the mitigation area
Seeding of slopes have been completed
As amenity items are confirmed/received they are being installed
General Construction Notes:
Construction is expected to continue through early fall. Work will occur Monday through Friday, between the hours of 7AM-5PM, weather permitting.
IDNR Perkinsville Public Access Site Update
NOTE: Starting on/after July 27th, the site will be closed to vehicles, boaters, anglers, and other visitors. The closure is necessary to provide a safe work environment for construction crews and the public.
During this closure, the following planned improvements will take place:
Widening the entrance drive and parking area
Enhancing and stabilizing river access
Completing related site grading and restoration work
Current Site Work Underway:
Scenic will be installing native seed mixture and wrapping up the bioretention area
Grubbing/clean up around concrete pad
Railing modification
E&B will have 4-5 days to install a culvert and perform additional stone installation/grading of the new parking surface (this will follow after all of the bioretention area work has been completed)
Things to Keep in Mind:
Construction vehicles entering/exiting the site along 8th St.
Residents and drivers are encouraged to use caution when traveling near construction zones
Potential, but minimal noise during active construction hours
ALL CONSTRUCTION NOTES
-
White River Greenway Eastern Park
Current Site Work:
Earthwork/grading – 9/3 and 9/4
Articulated mats at the end of the boat ramp installed-9/4 and 9/8
Site cleanup – Ongoing
Farm fence installation – Week of 9/7
Tentative Trail work – Week of 9/7
Seeding for areas not utilizing farm equipment – Week of 9/14
Remaining Site areas to be seeded – Week of 9/14 or 9/21
Riprap and tree removal at ramp – Week of 10/5
Tree planting mitigation area – Week of 10/5
Tree planting at Eastern property line – Week of 10/5
IDNR Perkinsville Public Access Site Update
NOTE: Starting on/after July 27th, the site will be closed to vehicles, boaters, anglers, and other visitors. The closure is necessary to provide a safe work environment for construction crews and the public.
During this closure, the following planned improvements will take place:
Widening the entrance drive and parking area
Enhancing and stabilizing river access
Completing related site grading and restoration work
Current Site Work:
Outlet pipe installed - 9/2
Finishing up earthwork – Week of 9/7
Concrete Pad installation – 9/3 and 9/4
Stone drive touch-up and grading – Week of 9/21
Seeding/plantings – Week of 9/28 into 10/5
-
White River Greenway Eastern Park
Current Site Work:
HMA paving has been completed.
Topsoil has been applied and will be prepped for seeding.
The concrete boat ramp has been finished.
General Construction Notes:
Construction is expected to continue through late summer. Work will occur Monday through Friday, between the hours of 7AM-5PM, weather permitting.
IDNR Perkinsville Public Access Site Update
NOTE: Starting on/after July 27th, the site will be closed to vehicles, boaters, anglers, and other visitors. The closure is necessary to provide a safe work environment for construction crews and the public.
During this closure, the following planned improvements will take place:
Widening the entrance drive and parking area
Enhancing and stabilizing river access
Completing related site grading and restoration work
-
Phase one construction of the White River Greenway Eastern Park site is officially underway.
Current Site Work:
Week of June 22nd: Construction activities continue with crews fine-grading the stone base in preparation for paving. Base asphalt paving is planned for Tuesday, June 23, through Wednesday, June 24, followed by topsoil placement and fine grading of disturbed areas from Wednesday, June 24, through Saturday, June 27. Crews are expected to complete surface asphalt paving on Monday, June 29, install shoulder stone along the pavement edges on Tuesday, June 30, and finish with pavement markings on Wednesday, July 1. This schedule is weather-dependent and subject to change.
-
Phase one construction of the White River Greenway Eastern Park site is officially underway. Current site work includes mass earthwork, excavation of the bio retention area, and building of the roadway/entrance into the park.
-
All permitting is approved
Eastern Park: Construction mobilization begins with earthwork the week ofApril 27th.
Construction of the Eastern Park will be underway first; the Perkinsville site construction is anticipated to start mid-summer.
-
Permit Updates-Approved & Issued
The IDNR permit for the Perkinsville Public Access Site was formally approved with a mail date of 3/18/26. The construction/development team is only awaiting the construction MOU from IDNR. IDNR has shared that this is a very high priority and they are moving it through their process as quickly as possible.
All necessary local, state, and federal permits for the Eastern Park have been received. The construction team will soon share 4-6 week construction outlooks to ensure the board is informed. We'll also use these 4-6 week outlooks to share construction updates directly on the Parks Department website.
Tree Clearing at Eastern Park & IDNR Perkinsville Public Access Site-Completed
Tree clearing began on 3/25 and was completed 3/30 at both the Eastern and Perkinsville sites. This work was completed prior to April 1st to comply with Indiana Law requiring that all tree clearing must happen before that date. This state law protects the Indiana Bat and its habitat.