CURRENT CONSTRUCTION UPDATE & PROGRESS PHOTOS

White River Greenway Eastern Park

Current Site Work: 10/27

  • Stone paths are scheduled to begin installation tomorrow and are expected to take approximately 2-3 days to complete.

  • Additional seeding will be completed after the stone path installation is finished.

  • Seeding for the grass/mowed paths, including the area adjacent to the Jackson property, has been completed.

  • Areas designated for wildflower growth have been disced and prepared.

  • The evergreen tree row along the Jackson property is anticipated to be planted within the next couple of weeks.

  • Riprap installation at the boat ramp has been completed.

  • The large tree near the ramp has been removed.

  • The concrete pad for the shelter is expected to be installed 1st/2nd week of November.

  • Bench and trash can pads have been laid out and are ready for concrete placement.

  • The installation schedule for the light pole foundations is currently being finalized.

General Construction Notes:

Construction is expected to continue through early fall. Work will occur Monday through Friday, between the hours of 7AM-5PM, weather permitting.

IDNR Perkinsville Public Access Site Update

NOTE: Starting on/after July 27th, the site will be closed to vehicles, boaters, anglers, and other visitors. The closure is necessary to provide a safe work environment for construction crews and the public.

View Closure Notice

During this closure, the following planned improvements will take place:

  • Widening the entrance drive and parking area

  • Enhancing and stabilizing river access

  • Completing related site grading and restoration work

Current Site Work Underway: Updated as of 10/27

  • E&B is scheduled to mobilize a stone crew later this week to complete the stone placement and grading work for the parking area.

  • Upon completion of the stone work, Scenic will return to perform final seeding and complete any remaining restoration and touch-up work.

Things to Keep in Mind:

  • Construction vehicles entering/exiting the site along 8th St.

  • Residents and drivers are encouraged to use caution when traveling near construction zones

  • Potential, but minimal noise during active construction hours