White River Greenway Initiative: Construction Updates- Summer/Fall 2026

CURRENT CONSTRUCTION UPDATE & PROGRESS PHOTOS

Eastern Park & Perkinsville Public Access Site Flooding & Construction Update

Historic flooding in August impacted both the Eastern Park construction site and the Perkinsville Public Access Site. As designed, floodwaters receded naturally at both locations, and none of the newly constructed infrastructure was damaged.

The Eastern Park site is located within a known floodplain, a condition understood and accounted for throughout the planning and design process. Parks and open spaces are commonly built in floodplain areas because they can accommodate periodic high water while keeping homes, businesses, and critical infrastructure out of harm’s way. The Eastern Park was designed to work with the natural landscape, including the reality that the White River will occasionally rise and portions of the site may temporarily flood.

The significant rainfall and saturated ground conditions have extended the construction timeline, primarily to provide the appropriate conditions for final planting, site restoration and remaining punch-list work. Construction at both sites is now anticipated to be substantially completed by early November with minor items by the end of November.

Madison County Parks and Recreation continues to work closely with the project team to ensure these improvements are completed thoughtfully and responsibly, with the long-term resilience and enjoyment of these riverfront spaces in mind.

Project Site Photos (09.03.26)

SEPTEMBER CONSTRUCTION UPDATE & SITE PROGRESS PHOTOS

White River Greenway Eastern Park

Current Site Work:

  • E&B’s path construction began 9/23

  • Staking for paths have been completed and grass is to be installed in the areas that have been staked but will not be stone

  • Intent is to allow for a mowed path that eventually can be converted stone

  • On/After 10/1 the maple tree at the end of the boat ramp will be cut down

  • Riprap work at boat ramp will happen after the tree has been cut to help allow for better grading and placement of material to protect the boat ramp

  • Mid-October, the HMA surface, pavement markings, and stone shoulder will be installed, trees will also be installed within the mitigation area

  • Seeding of slopes have been completed

  • As amenity items are confirmed/received they are being installed

General Construction Notes:

Construction is expected to continue through early fall. Work will occur Monday through Friday, between the hours of 7AM-5PM, weather permitting.

IDNR Perkinsville Public Access Site Update

NOTE: Starting on/after July 27th, the site will be closed to vehicles, boaters, anglers, and other visitors. The closure is necessary to provide a safe work environment for construction crews and the public.

View Closure Notice

During this closure, the following planned improvements will take place:

  • Widening the entrance drive and parking area

  • Enhancing and stabilizing river access

  • Completing related site grading and restoration work

Current Site Work Underway:

  • Scenic will be installing native seed mixture and wrapping up the bioretention area

  • Grubbing/clean up around concrete pad

  • Railing modification

  • E&B will have 4-5 days to install a culvert and perform additional stone installation/grading of the new parking surface (this will follow after all of the bioretention area work has been completed)

Things to Keep in Mind:

  • Construction vehicles entering/exiting the site along 8th St.

  • Residents and drivers are encouraged to use caution when traveling near construction zones

  • Potential, but minimal noise during active construction hours

ALL CONSTRUCTION NOTES