We are moving into spring construction season. Please use this page to find the latest updates related to construction activities. Note: All activities and timelines can be impacted by weather.
March Construction Notes
Permit Updates-Approved & Issued
The IDNR permit for the Perkinsville Public Access Site was formally approved with a mail date of 3/18/26. The construction/development team is only awaiting the construction MOU from IDNR. IDNR has shared that this is a very high priority and they are moving it through their process as quickly as possible.
All necessary local, state, and federal permits for the Eastern Park have been received. The construction team will soon share 4-6 week construction outlooks to ensure the board is informed. We'll also use these 4-6 week outlooks to share construction updates directly on the Parks Department website.
Tree Clearing at Eastern Park & IDNR Perkinsville Public Access Site-Completed
Tree clearing began on 3/25 and was completed 3/30 at both the Eastern and Perkinsville sites. This work was completed prior to April 1st to comply with Indiana Law requiring that all tree clearing must happen before that date. This state law protects the Indiana Bat and its habitat.
April Construction Activities
We are awaiting confirmed dates for earthwork at the Eastern Park; it could begin as soon as mid-to-late April. Construction of the Eastern Park will begin first; Perkinsville site construction is anticipated to start mid-summer.